Process Blog for the design, construction, and use of housing for the One Acre Fund in Bungoma,Kenya; designed by Kit and Sam Kollmeyer, built by Construction for Change. The design process began in July and was completed in November 2009. The construction will begin in January of 2010.

Sunday, March 21, 2010

Beginning Buildings 2 & 3

electricity arrives to Building 1
plastering
beginning foundations of Buildings 2 & 3

finished interior of kitchen in Building 1

Roofing Building 1






Tuesday, March 2, 2010

After Delay Gears Turning Again

arrival of security grating
installing security grating
Alex digging the hole for pit latrine (12' deep here of 21' total)
installing courtyard drain (yet to be buried) and pouring porch slab
rear porch slab covered with banana-leaf-improv-sheet for the evening's rain